|
What factors
determine Cretexs required delivery lead-time?
In order to give and meet a delivery schedule the following factors are
considered:
- Previously
scheduled production
- Availability
of complete contract drawings and agreed upon scope of work
- Drafting
availability
- The complexity
of the project
If production
space, Cretex engineering services, and complete contract drawings were available,
how fast a schedule could be available for a "simple" 30,000
square foot building using precast wall panels?
The following schedule would be achieved:
- Week 0:
Complete Contract Drawings and Purchase Order Received
- Week 2:
Cretex Shop Drawings Submitted
- Week 4:
Approved Shop Drawings Returned To Cretex
- Week 5:
Production Begins
- Week 7:
Production Completed & Delivery Begins
- Week 8:
Delivery Complete
What are
the most common reasons for the schedule cited above not being available?
The most common reason is that useable for construction documents are
not available at the time a project is presented to Cretex. Although we are
happy to begin the drawing process and work to identify the missing details,
this does result in a lengthening of the shop drawing submittal process.
It is also common during the peak season for Cretexs production lead-time
to extend beyond eight weeks.
Should Cretex
expand if its production schedule is causing long lead-times?
Yes, Cretex continually looks to expand its capabilities for sustainable
growth in demand for our products. Cretex has added several production facilities
allowing our plants to double production capacity since the early 1990s.
Can Cretex
react to short-term changes in the demand for its products?
The capital-intensive nature of our business, coupled with the labor shortage
faced by all businesses makes it difficult to significantly increase our
capacity for a short period of time. The seasonality often experienced
in construction may cause lead-times to grow during the heaviest construction
months. We do undertake weekend work to meet our committed schedules.
Also, Cretex will continue to expand its facilities in an attempt to meet
the long-term demands of the construction market.
How can
a customer reserve space in Cretexs schedule before complete construction
documents are ready and pricing has been finalized?
In order to reserve a space, Cretex requires a letter of intent on the project
as well as a schedule for the release of for construction documents and
a schedule for the issuance of a purchase order. Also, the schedule for
the release of contract drawings must be far enough in advance of production,
so that Cretex can fill the production space with other work if the schedule
is not met. The consistency of work performed by Cretex and the contractor
also impacts our ability to save the space.
Why wont
Cretex save a space without a letter of intent?
In order to keep our workforce employed, we need to ensure that firm commitments
are in place and that the schedules of Cretex, the architect, the engineer,
and the general contractor are achievable. The absence of a commitment
has, in the past, resulted in job delays requiring us to lay off plant
employees.
Can Cretex
establish a reliable budget for its product on your project?
Cretex is able to give budget pricing at an early stage in the project design
process. It is Cretexs desire to ensure that our final pricing falls
within the budgeted range unless significant changes to the concept were
made. If Cretex becomes aware of such changes, we will immediately notify
the customer that the budget price no longer applies. We will then supply
a new budget number, if required.
Will I pay
more by getting budget pricing and committing to Cretex early in the project?
No, the market for precast is competitive and Cretex maintains our pricing
to help ensure that projects proceed. In addition, Cretex benefits by these
early commitments as they allow us to do capacity planning, provide value
engineering and assure on-time delivery.
What does
the "schedule note" on Cretexs quotation mean?
Cretex attempts to give customers an idea of our lead-time by stating the
next available production space as of the day the quotation is prepared.
This schedule note is intended to assist the customer in identifying where
lead-time issues will be critical and can allow the customer to communicate
with the owner as to a required time frame for deciding to proceed with
the job. Due to the uneven flow of orders, we are unable to predict how
the lead-time will change in the weeks following the quotation. A schedule
commitment can be made by Cretex when a purchase order and complete contract
drawings are received.
What can
a customer do to get the best possible schedule?
Early communication with an Cretex sales representative with on-going communication
between Cretex and you will help ensure that a satisfactory schedule can
be set and, more importantly, met.
|